What a task's page shows, how to change its owner, status, dates and progress in place, what each tab is for, and the actions in its Actions menu.

Updated in release 0.0.1 Needs permission from your admin

In the sidebar, open Projects & Tasks, then Tasks, and open a task from the list. The page address is /work/tasks/ followed by the task and the tab you are on. It is laid out like every record page (see Find your way around a record page). A task has no separate edit page: you change it right on this page.

What you see

  • The summary strip: what the task hangs off (an account, project, work order or parent task), the Task Number, the Owner, the Progress and the Timeline.
  • The details panel on the left, where you edit the task:
    • Parent context: the account, portfolio, project, work order and parent task it belongs to.
    • Task details: press the title to rename it. Change the Status, the Phase, the Owner, the Parent Task, and the Start and Due dates. Each change saves as soon as you pick it. Set the status to a done status to finish the task (Complete or archive a task).
    • Description: type, then press Save. Only your team sees it.
    • Delivery: Priority, Progress Mode (Derived works it out for you; Manual lets you type the Manual Progress percentage), the Estimate in minutes, the Logged Time, Child Tasks and Tags.
    • Additional details: your organization's own fields.

The tabs

Some tabs only appear when your plan includes the feature.

The Actions menu

  • Back to tasks, Add note and Upload file.
  • Save as template saves the task as a task template (Create a task template).
  • Customize tabs (Change the tabs on one customer or record).
  • Archive task, last and in red. Archive task? warns that its subtasks go too; nothing is deleted. An archived task shows a banner with Restore, and Restore task heads the menu.

If something looks different

  • The fields are greyed out: your role cannot update tasks, or you are looking at an archived task.
  • Owner is greyed out while other fields work: your role cannot reassign tasks.
  • People, Subtasks, Dependencies, Time, Execution or Comments is missing: that feature is not part of your plan, or an admin hid the tab.